Submitted by Kris Boone, boone.3@osu.edu
The Halterman Hall Generator is in the process of being replaced, there are two transfer switches that need to be installed and connected. There will need to be a controlled power down of the electric that feeds the two switches. The following will be affected by this power down on December 14th (2 hours), December 15th (4 hours).
Total outage: Consultation with FDC electrical team and Jeff Strouse.17
- Internet room 71M
- L&B greenhouse
- Grounds Shop
- Construction/Landscaping Lab
- Halterman Boilers and Chilled-Water Pumps
- Fire alarm power to the main panel. Jeff Strouse will notify the Columbus Fire Alarm monitoring before the power goes off to the panel and the battery should keep the system running until power is restored
Networking Systems (no internet) Consultation with Cort Sutherland.172
- Skou
- Halterman
- SAC
- Feed Mill
- All of Grace Drake Farms
- Kraus Dairy
- Snyder Farm
- Oil City Road Buildings